SOLUTION: A can do a piece of work in 3 days B can do it in 4 1l2 days.how long will they take to complete the work if they work together?sir pls give me its full steps?
Algebra.Com
Question 840907: A can do a piece of work in 3 days B can do it in 4 1l2 days.how long will they take to complete the work if they work together?sir pls give me its full steps?
Answer by hamsanash1981@gmail.com(151) (Show Source): You can put this solution on YOUR website!
A can do a piece of work in 3 days and B in 4 1/2 ie 9/2 days then,
A's one day work is 1/3 and B's one day work is 1/(9/2) => 2/9
A+B 's one day work = 1/3 + 2/9
= (3+2)/9
= 5/9
A+B can complete the work in 9/5 days or 1 4/5 days
RELATED QUESTIONS
John can complete a piece of work in 3 days. Jojce can do it in 9 days and James can do... (answered by ewatrrr)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
A and B can do a piece of work in 40/3 days. A alone can do the work in 20 days. How long (answered by mananth)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
Isaac alone can do a piece of work in 5 days, and his wife, Esther also can do it in... (answered by ankor@dixie-net.com,ikleyn)
P can do a piece of work in 20 days and Q in 24 days. find how much time will they take... (answered by richwmiller)
P can do a piece of work in 20 days and Q in 24 days. find how much time will they take... (answered by richwmiller)
B will take 3 days longer than A to complete a piece of work. If they together can... (answered by richwmiller)