SOLUTION: 6 men take 4 days to complete a part of a job. how many days will it take 8 men to do the same piece of work?
Algebra.Com
Question 320389: 6 men take 4 days to complete a part of a job. how many days will it take 8 men to do the same piece of work?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
6 men take 4 days to complete a part of a job.
how many days will it take 8 men to do the same piece of work?
;
this is easy using man-days
:
6 * 4 = 24 man-days to complete job
:
Let d = no. of days for 8 men
8d = 24
d = 24/8
d = 3 days for 8 men to do it
RELATED QUESTIONS
If three men take 3 days to complete a piece of work, how many days will 2 men take to... (answered by reynard2007)
15 men take 21 days of 8 hours each to do a piece of work. How many days
of 6... (answered by richwmiller)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
if four men do a piece of work in 8 days how many days will it take 16 men working at the (answered by ewatrrr)
4 men can do a piece of work in 8 days how many days would it take
16 men at the same... (answered by Edwin McCravy,ikleyn,josgarithmetic,greenestamps)
If it takes 6 men to do a job in 4 days how many days will it take 2... (answered by oscargut)
if five men can do a piece of job in twenty-five days, how many days will it take ten men (answered by ewatrrr)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)