Question 315741: A contractor estimated that 30 ft^3 of cement is required to make a concrete floor that measure 90 ft^2. Using this estimate, how much cement is required to make a concrete floor that measures 120ft^2?
Answer by checkley77(12844) (Show Source): You can put this solution on YOUR website!
The answer of 10ft^2 doesn't make sense.
You are asked to increase the area by 33%.
Therefore you'll nned 33% more cement ASSUMING the depth of the cement is the same.
Thus the amount of cement will be 33% greater or:
90=x/120
90x=30*120
90x=3,600
x=3,600/90
x=40 ft^3 of cement will be required.
You asked how much cement is requird. The answer is 30Yds^2
IF you had asked how much MORE cement would be required then 10^2 would be correct.
RELATED QUESTIONS
A contractor estimated that 30 ft^3 of cement is required to make a concrete floor that... (answered by rfer)
A contractor estimated that 30 ft^3 of cement is required to make a concrete floor that... (answered by josmiceli)
A contractor estimated that 30 ft3 of cement is required to make a concrete floor that... (answered by Cromlix)
The density and strength of concrete are determined by the ratio of cement and aggregate
(answered by josgarithmetic)
A certain mixture for concrete is in the amounts of 1:2:4;
1 cu. ft. of cement.
2... (answered by ikleyn)
A concrete mix is in volume proportions of 1 part cement, 2 parts water, 2 parts... (answered by HyperBrain)
A concrete mix is in volume proportions of 1 part cement, 2 parts water, 2 parts... (answered by edjones)
A contractor mixed two batches of concrete that were 9.3 and 11.3 percent cement to... (answered by Earlsdon)
please help me on this problem!
A contractor has been assigned the job of painting the... (answered by solver91311)