Initial number: 3,600
Target number remaining: 2,000
Amount to be shipped: 3,600 - 2,000 = 1,600
Number of weeks to ship 1,600 computers, at a rate of 128 per week:
That's IT!! Nothing more...Nothing less!! No complexities! No algebra, just sheet logic and common sense!