Question 1139743: X can do a job in 16 days Y can do the same job in 20 days if X,Y and Z can do the job in 7.5 days . Alone Z can do the same job in ...?
Answer by ikleyn(52781)   (Show Source): You can put this solution on YOUR website!
.
Rate of work for X is    of the job per day.


Rate of work for Y is    of the job per day.


The combined rate of work for X, Y and Z is   =   of the job per day.


Hence, the individual rate of work for Z is   = (the common denominator is 240) =  =  =  = .


It means that Z will complete the job in  48 days working alone.    ANSWER

Solved.

-------------------

It is a standard and typical joint work problem.

There is a wide variety of similar solved joint-work problems with detailed explanations in this site.  See the lessons
    - Using Fractions to solve word problems on joint work
    - Solving more complicated word problems on joint work
    - Selected joint-work word problems from the archive


Read them and get be trained in solving joint-work problems.

Also,  you have this free of charge online textbook in ALGEBRA-I in this site
    - ALGEBRA-I - YOUR ONLINE TEXTBOOK.

The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems"  of the section  "Word problems".


Save the link to this online textbook together with its description

Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson

to your archive and use it when it is needed.


/\/\/\/\/\/\/\\/\/

Hey, I have a question.

Today I solved several similar problems for you.

Hope I helped you and taught you something.

Are you familiar with the conception that you should thank for the help ?

Did your parents, or your relatives, or in the school educate / teach you to do it ?

I still do not see your "Thanks" in my post box.



RELATED QUESTIONS

X, Y and Z can do a job in 10 days. X leaves after working with Y and Z for 4 days, and... (answered by richwmiller)
If Sam can do a job in 4 days, Lisa can do the same job in 6 days, and Tom can do the job (answered by stanbon)
If X people can do a job in D days, how long would it take Y people to do the same... (answered by Alan3354)
if 3 men can repair the house in 20 days,how many days can 5 men do the same... (answered by ankor@dixie-net.com)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
Hi 10 men and 20 women can do a job in 15 days. 15 men and 10 women can do the same job... (answered by VFBundy)
Y men can do a job in 20 days. They work for 8 days and rest for 4 days. For them to... (answered by ankor@dixie-net.com)
3 men can do the job of 4 women. If 3 men can do a job in 8 days, in how many days can 5... (answered by richwmiller)
Machine X can do a certain job in four hours and machine Y can do the same job in six... (answered by josgarithmetic)