Let time A takes be A
Then when A, B, and C work together, they perform:of work, respectively
Then we get:
4(18) + 4(2A) + 9A = 18A ------- Multiplying by LCD, 18A
72 + 8A + 9A = 18A
72 = 18A - 17A
Time A takes to do the job, alone, or
Let "a" be the A's rate of work. From the condition, rate of work for B isand rate of work for C is . Also, we are given that a + + = . Therefore, a = - - = - - = . Thus, A's rate of work is , which means that A can complete the job in 72 days, working alone.