The time to complete a project is inversely proportional to the number of people who are working on the project. A class project can be completed by 3 students in 20 days. In order to finish the project in 5 days how many more students should the group add?
I got 3/20=x/5
Then I cross multiply
20x=15
Then I divided both sides by 20x which I got 0.75
Please help I know the answer is wrong but I cannot figure out the answer
k = 3(20), or 60
------- E being the extra students needed
3 + E = 12
E, or extra students needed = 12 – 3, or