Question 869447: It takes one crew 4 hours to clean an auditorium after an event. If a second crew helps, it only takes 2.5 hours. How long would it take the second crew, working alone, to clean the auditorium?
_____hours?
Answer by LinnW(1048) (Show Source): You can put this solution on YOUR website!
Crew 1 takes 4 hours so their rate is (1/4)auditorium per hour
Let x be the rate in auditoriums per hour of Crew 2
( 1/4 + x )( 2 1/2 hours ) = one clean auditorium
( 1/4 + x )( 5/2 ) = 1
multiply each side by 2/5
( 1/4 + x ) = 2/5
add -1/4 to each side
x = 2/5 -1/4
x = 8/20 -5/20
x = 3/20
3/20 represents 3 auditoriums per 20 hours
or 1 auditorium every 6 2/3 hours ( divide 20 by 3 to get this )
RELATED QUESTIONS
It takes one crew 8 hours to clean an auditorium after an event. If a second crew helps,... (answered by richwmiller)
if it takes a crew 8 hours to finish cleaning the auditorium if the second group help it... (answered by checkley79)
If it takes a janitorial crew 6 h to clean a company’s offices, then in x hours the... (answered by josgarithmetic,greenestamps)
A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
If three people working together can clean an office suite in two hours, how long will it (answered by solver91311,bucky)
It takes crew A 4 hours to paint a room. It takes crew B 5 hours to do the same job. How... (answered by josmiceli,Edwin McCravy)
A new crew of painters takes two times as long to paint a small apartment as an... (answered by richwmiller)
If it takes 5 people 7 hours to clean an office building, how long would it take 4 people (answered by scott8148)
A contractor finds that Crew A takes 5(1/2) hours to construct a retaining wall and Crew (answered by ankor@dixie-net.com)