SOLUTION: 14 men took 6 hours 40 min to complete a job a. How long will it take 8 men, working at the same rate to complete the same job? b. If 2 of the 8 men leave the job after working f

Algebra.Com
Question 847181: 14 men took 6 hours 40 min to complete a job
a. How long will it take 8 men, working at the same rate to complete the same job?
b. If 2 of the 8 men leave the job after working for 1 hour, how long will it take the remaining 6 men working at the same rate to complete the job
Thanks I got question a but can't figure out b

Answer by josgarithmetic(39616)   (Show Source): You can put this solution on YOUR website!
For part a, should we assume it is each man works at the same rate as in the previous description? Or does the question mean that the group of 8 men work at the same rate as the group of the 14 men? If the groups work at the same rate, then the group of 8 men would also need 6 hours 40 minutes to complete a job.

That makes question part b unclear. Taking the question part b exactly as it is stated, no assumptions, the 8 men would complete 1 job in 6 hours 40 minutes, which is hours. (SAME RATE AS THE DESCRIBED 14-MAN GROUP!). The one-man rate for this is jobs per hour.

As a uniform rates task completion situation, R*T=J, rate, time, job amount. One hour at one rate, an unknown time at another rate. Eight men work for 1 hour, and then 6 men work for some time t, and this completes the one job:

Solve for t.
-
You may want to interpret differently about the one-man rate. You might want to find the one-man rate based on the group of the 14 men as described first in the problem description. You might really want the one man rate to be taken as jobs per hour

RELATED QUESTIONS

14 men took 6 hours and 40 minutes to complete a job. if two of 8 men leave after... (answered by ankor@dixie-net.com)
given that it takes 6 hours for 12 men to complete a certain fob, find (i) how long will... (answered by ewatrrr)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
12 men took 8 hour and 40 min to complete a job a. Find the time taken for 8 men to... (answered by josgarithmetic,ankor@dixie-net.com)
Five men take 12 days to complete a job. How long will 8 men take at the same... (answered by mananth)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)
7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take... (answered by ikleyn)
10 men can complete a job in 14 days.how long will it take 4 men to finish same job if... (answered by josmiceli,josgarithmetic)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)