SOLUTION: Three men can do the job at painting a house in 37 days.If another 6 men joined them 7 days after they started painting.How many more days will they finish painting?

Algebra.Com
Question 460075: Three men can do the job at painting a house in 37 days.If another 6 men joined them 7 days after they started painting.How many more days will they finish painting?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Three men can do the job at painting a house in 37 days.
Find the number of man-days to do the job
3 * 37 = 111 man-days to paint the house
:
If another 6 men joined them 7 days after they started painting.
How many more days will they finish painting?
:
Let d = no. of man days to complete the job,
After 7 days there will be 9 men working.
:
3(7) + 9d = 111
21 + 9d = 111
9d = 111 - 21
9d = 90
d = 10 days to finish the house

RELATED QUESTIONS

Twelve men can complete a work in 8 days. Three days after they started the work, 3 more... (answered by Edwin McCravy)
45 men can complete the work in 16 days. four days after they started working, 36 more... (answered by fractalier)
12 men can do a job in 8 days. If after 5 days,they are joined by 4 more men, how many... (answered by ankor@dixie-net.com)
1.four men can paint a house in 24 days.the owner wants the painting job to be finished... (answered by stanbon)
Dimple can finish painting her room in 10 days. She started the job alone and after... (answered by ikleyn)
Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days... (answered by nshah11,hibiskus)
6 men take 2 days to paint a house. how long would 2 men take to do the painting ? (answered by htmentor,w_parminder)
a painting job can be completed by 7 painters in 17 days. if 21 more painters joined the... (answered by ankor@dixie-net.com)
16 men can finish a work in 12 days. After they worked for 4 days, some more men joined... (answered by ikleyn,josgarithmetic)