SOLUTION: Twenty men did 1/4 of a job in 8 days. Then, because of an emergency, it became necessary to complete the job in the next 5 days. How many additional men were added to the crew of
Algebra.Com
Question 300148: Twenty men did 1/4 of a job in 8 days. Then, because of an emergency, it became necessary to complete the job in the next 5 days. How many additional men were added to the crew of 20 to accomplish this?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
Twenty men did 1/4 of a job in 8 days.
:
Find the total number of man-days to complete 1/4 of the job
20 * 8 = 160 man-days
:
Then, because of an emergency, it became necessary to complete the job in the next 5 days.
How many additional men were added to the crew of 20 to accomplish this?
:
Let x = no. of additional men required
:
3 * 160 = 480 man-days required to complete the remaining 3/4 of the job
:
(x+20)*5 = 480
5x + 100 = 480
5x = 480 - 100
5x = 380
x =
x = 76 additional men required to complete the job in 5 yrs.
:
:
Check: 5(76+20) = 480 man-days
RELATED QUESTIONS
Twenty men did 1/4 of a job in eight days. Then it became necessay to complete the job... (answered by ankor@dixie-net.com)
25 women did 1/5 of job in 8 days. Then, because of an emergency, it became necessary to... (answered by Edwin McCravy)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the... (answered by josmiceli)
5 men are hired to complete a certain job. if an additional men is hired, the job can be... (answered by ikleyn)
Y men can do a job in 20 days. They work for 8 days and rest for 4 days. For them to... (answered by ankor@dixie-net.com)
24 men complete a job in 40 days. The number of men required to complete the job in 32... (answered by JulietG)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
60 men worked 12 days on a job. How many men would it take to complete the same job in 8... (answered by nyc_function)