Question 289059: It takes 7.5 hrs for 16 people to place flyers on each of the kiosks on campus. How long would it take 13 people?
Any help would be greatly appreciated.

Answer by checkley77(12844)   (Show Source): You can put this solution on YOUR website!
7.5*16=120 manhours are required.
13x=120
x=120/13
x=9.23 hours.

RELATED QUESTIONS

Im having difficulty figuring this question out.What is the correct units. Round to... (answered by jayanthihemkos@yahoo.com)
Mary is printing flyers for a campus event. She is using two printers to make the copies, (answered by josgarithmetic)
If it takes 10 people 7 hours to paint the front of the office building, how long will it (answered by josmiceli)
the time it takes to complete a certain job varies inversely to the number of people... (answered by stanbon)
If it takes 5 people 7 hours to clean an office building, how long would it take 4 people (answered by scott8148)
Jack, Kay, and Lynn deliver advertising flyers in a small town. If each person works... (answered by josgarithmetic,greenestamps)
It takes 45 min for 2 people to shovel a driveway. How long would it take 5 people to... (answered by stanbon)
if it takes 3 people 8 hrs to do a job how long will it take 2... (answered by solver91311)
Jack, Kay, and Lynn deliver advertising flyers in a small town. If each person works... (answered by ankor@dixie-net.com)