Question 198523: A can do a piece of work in 18 days and B can do it in 21 days. A, B, and C together can finish the work in 7 days. How long will it take C alone to finish the work?
Answer by Edwin McCravy(20054)   (Show Source): You can put this solution on YOUR website!
A can do a piece of work in 18 days and B can do it in 21 days. A, B, and C together can finish the work in 7 days. How long will it take C alone to finish the work?

Let x be the number of days C to finish the work.

Make this chart, filling in 1's for the number of pieces of work,
since exactly 1 was done in each case.  Then fill in the given
times and the unknown time x for C

        PIECES OF WORK  =    RATE  * TIME
A             1                       18
B             1                       21
C             1                        x
----------------------------------------
A&B&C         1                        7

        
Now we fill in the rates in pieces of work per day,

using 

        PIECES OF WORK  =    RATE  * TIME
A             1              1/18     18
B             1              1/21     21
C             1               1/x      x
----------------------------------------
A&B&C         1               1/7      7


So we add up the rates of A, B, and C and that must equal
to their combined rate. We get it all from the middle
column:



Can you solve that for x?  Answer: days. 

Edwin

RELATED QUESTIONS

A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a... (answered by ikleyn)
A can do a piece of work in 16 days and B can do it in 20 days. These worked together for (answered by robertb)
A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days.... (answered by ptaylor,Edwin Parker)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a can (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
A can do a piece of work in 2 days as B can do in 3 days. B can do as much work in 4 days (answered by ankor@dixie-net.com)