SOLUTION: Twenty men did 1/4 of a job in eight days. Then it became necessay to complete the job in the next five days. How many additional men were added to the crew of twenty to accomplis

Algebra.Com
Question 140309: Twenty men did 1/4 of a job in eight days. Then it became necessay to complete the job in the next five days. How many additional men were added to the crew of twenty to accomplish this task?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Twenty men did 1/4 of a job in eight days. Then it became necessary to complete the job in the next five days. How many additional men were added to the crew of twenty to accomplish this task?
:
From the information given, find out how many man-days required to complete the job
20 * 8 * 4 = 640 man-days to complete the job
:
Find out how many man-days required to finish the remaining 3/4 of the job.
:
*640 = 480 man-days
:
Let x = no. of additional men required to did this in 5 days
:
5(20+x) = 480
:
100 + 5x = 480
:
5x = 480 - 100
x =
x = 76 more men required
:
Check
1st 20 men worked: 20 * 8 = 160 man days
2nd 96 men worked: 5 * 96 = 480 man days
------------------------------------------
Total to do the whole job = 640 man days

RELATED QUESTIONS

Twenty men did 1/4 of a job in 8 days. Then, because of an emergency, it became necessary (answered by ankor@dixie-net.com)
eight men can complete a job in 25 days. how many men will be needed to complete the job... (answered by psbhowmick)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
25 women did 1/5 of job in 8 days. Then, because of an emergency, it became necessary to... (answered by Edwin McCravy)
if five men can do a piece of job in twenty-five days, how many days will it take ten men (answered by ewatrrr)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the... (answered by josmiceli)
Twenty men can finish the job in 30 days. Twenty five men were hired at the start and 10... (answered by josgarithmetic)
60 men worked 12 days on a job. How many men would it take to complete the same job in 8... (answered by nyc_function)