SOLUTION: Hi 6 men do a job in 8 days. After 3 days 2 of the men are taken off the job. Find the time it takes for the job to be completed from start to finish. Thanks

Algebra.Com
Question 1184255: Hi
6 men do a job in 8 days. After 3 days 2 of the men are taken off the job. Find the time it takes for the job to be completed from start to finish.
Thanks

Found 2 solutions by math_helper, greenestamps:
Answer by math_helper(2461)   (Show Source): You can put this solution on YOUR website!

One approach is to figure out how much work ONE man does in ONE day (the unit rate of work per person). Once you know that, the rest falls into place easily.
6 men do the entire job in 8 days
That means 6 men do 1/8 of a job in one day
And one man does (1/6)*(1/8) = 1/48 job in one day

How much work is done in the first three days?
3days * 6men * (1/48 job/day/man) = 18/48 job
This leaves (48/48) - (18/48) = 30/48 of the job to do by the remaining 4 men:
Say it takes N more days...
4 * (1/48) * N = 30/48
N = (30/48) * (48/4) = 7.5 days

Therefore, the entire job takes 3 days + 7.5 days = days.
Check: 3men * 6days * (1/48 job/day/man) + 7.5days * 4men * (1/48 job/day/man) = 48/48 = 1 job (ok)

Answer by greenestamps(13203)   (Show Source): You can put this solution on YOUR website!


Here are two other ways -- among many different possible ways -- of solving the problem.

Look at different ways and find what "works" best for you....

(1) After the first 3 days, there is enough work for the 6 men for another 5 days.

When 2 men are taken off the job, there are 4 men left; the number of workers gets multiplied by a factor of 4/6=2/3.

That means the amount of time remaining to finish the job gets multiplied by a factor of 3/2. So the number of days needed to finish the job is 5(3/2)=7.5

And so the job from start to finish takes 3+7.5 = 10.5 days.

(2) The entire job takes 6*8 = 48 man-days to complete.

The 6 men working for the first 3 days work a total of 6*3=18 man-days; there are 48-18=30 man-days of work remaining.

The number of days it takes 4 men to do the remaining 30 man-days of work is 30/4=7.5.

The total time for the job from start to finish is 3+7.5 = 10.5 days.


RELATED QUESTIONS

A Certain Job Can Be Done By 8 Men In 20 Days. After 5 Days, 3 Men Left The Job. How... (answered by Theo,Fombitz)
It takes 8 men 3 days to paint the outside of a house how long does it take 6 men to do... (answered by Edwin McCravy)
5 men are hired to complete a certain job. if an additional men is hired, the job can be... (answered by ikleyn)
It takes 15 days for 2 men to repair the house.How many men are needed to complete the... (answered by thesvw)
Q1. if 2 men or 3 women or 6boys can do a piece o work in 70 days,in what time would 2... (answered by ankor@dixie-net.com,vvnrichards)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
6 men and 9 women require 10 days to complete a job. How much time will 8 men and 3 women (answered by josmiceli,vvnrichards)
12 men took 8 hour and 40 min to complete a job a. Find the time taken for 8 men to... (answered by josgarithmetic,ankor@dixie-net.com)