Question 1143847: Hi
one team of workers completes a job in 10 days, while another team completes it in 8 days. The first team worked alone for 1 day. Then the second team joined and finished the job in N days. What is the value of N.
thanks

Found 3 solutions by greenestamps, josgarithmetic, ikleyn:
Answer by greenestamps(13200)   (Show Source): You can put this solution on YOUR website!


Working together the whole time, the number of days it would have taken to do the job is



But in the beginning only the first team worked for 1 day, completing 1/10 of the job. Since only 9/10 of the job remains, the number of days it takes the two team together to finish the job is



ANSWER: N = 4

Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
OneTeam
AnotherTeam
CombinedTeams

--

The actual work done described:
Solve for N.

Answer by ikleyn(52781)   (Show Source): You can put this solution on YOUR website!
.
One team of workers can complete the job in 10 days -- hence, the rate of work of this team is    of the job per day.


The other team of workers can complete the job in 8 days -- hence, the rate of work of the other team is    of the job per day.


The combined rate of work of two teams working together is   =  =  of the job per day.


After working first day, the first team completed    of the job -- hence,    of the job remained to do.


Working at the combined rate    of the job per day, the two team need   =  = 4 days to complete the job.


Thus "N", the number of days under the question is 4:  N= 4.    ANSWER

Solved.

-------------------

It is a standard and typical joint work problem.

There is a wide variety of similar solved joint-work problems with detailed explanations in this site.  See the lessons
    - Using Fractions to solve word problems on joint work
    - Solving more complicated word problems on joint work
    - Selected joint-work word problems from the archive


Read them and get be trained in solving joint-work problems.

Also,  you have this free of charge online textbook in ALGEBRA-I in this site
    - ALGEBRA-I - YOUR ONLINE TEXTBOOK.

The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems"  of the section  "Word problems".


Save the link to this online textbook together with its description

Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson

to your archive and use it when it is needed.


RELATED QUESTIONS

Hi Two teams completed a job in 8 days. The rate of work of the first team was 5/8 of... (answered by josgarithmetic)
Two teams of workers have to a work in 6 days. After the that the first team worked 5... (answered by ptaylor)
Two teams of workers have to do a job in 6 days.After that the firstteam worked 5 days ,... (answered by stanbon)
Hi If 2 teams work together they can finish a job in 8 days. The rate of work of... (answered by josmiceli,ikleyn,greenestamps)
two teams of construction workers had to renovate for 12 days. after 8 days during which (answered by josgarithmetic,ikleyn)
A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take to (answered by TimothyLamb)
A gardener completes 5/8 of his landscaping job in 10 days. At this rate how many days... (answered by stanbon)
A team of 2 men and 5 women completed one –fourth of a job in 3 days. After 3 days... (answered by stanbon)
One group of workers can do a job in 8 days. After this group has worked 3 days, another... (answered by mangopeeler07)