SOLUTION: Hi it takes 15 days for 10 workers working 8 hours a day to finish an order. How many workers working 4 hours a day would be needed to finish the order in 10 days. thanks

Algebra.Com
Question 1131997: Hi
it takes 15 days for 10 workers working 8 hours a day to finish an order. How many workers working 4 hours a day would be needed to finish the order in 10 days.
thanks

Found 4 solutions by joshuajz, josgarithmetic, ikleyn, greenestamps:
Answer by joshuajz(12)   (Show Source): You can put this solution on YOUR website!
15 people w/ 80 hours of work being done a day. That's a total 1200 hours to complete the project. 1200/10 = 120 hours needed a day. 120/4 = 30 workers.
Therefore 30 workers are needed.

Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
--------------15 days at 10 hours per day is 120 hours.


-------------n workers, for 10 days at 4 hours per day, same ONE ORDER






Answer by ikleyn(52802)   (Show Source): You can put this solution on YOUR website!
.
Use the proportion

 = ,


where x is the unknown number of workers under the question.


The proportion says that the rate of work of each single worker is the same, measured in parts of the total job per hour per worker.


From the proportion,  find  x =  =  = 15*2 = 30 workers.     ANSWER


By doing in this way, you have easy way to create an equation (a proportion) based on clear idea of the rate of work.


So, you will never make a mistake in this way.

-----------------

To see many other similar solved problems,  look into the lesson
    - Rate of work problems
in this site.


Answer by greenestamps(13200)   (Show Source): You can put this solution on YOUR website!


You already have three responses showing very different ways of solving problems like this. All are very good methods; different students will have preferences for different methods. Find a way that "works" for you.

Here is the method I use because it "works" best for me.

Compare each of the new parameters to the given parameters and see how it changes the number of workers required:
(1) 4 hours a day instead of 8: keeping the number of days the same, half as much time each day means 2 times as many workers. 10*2 = 20.
(2) 10 days instead of 15 days: keeping the number of hours per day the same, 2/3 as many days means 3/2 as many workers. 20*3/2 = 30.

Answer: You need 30 workers to do the same job in 10 days working 4 hours a day.

RELATED QUESTIONS

1) It took 24 workers working 10 hours per day for 24 days to complete a task. At this... (answered by ankor@dixie-net.com)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
A man and a boy perform a task in 2 days. They completed one-half of the task with the... (answered by ankor@dixie-net.com)
If it takes 3 days for 10 workers to finish a house, how many days will it take 15... (answered by ankor@dixie-net.com)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)
10 men working for 5 hours a day for 6 days mow an area of 5 acres. If there are 8 men... (answered by josmiceli)
if 4 painters complete a painting job in 15 days working hours per day, how long would it (answered by ankor@dixie-net.com)
12 men working 7 hours a day can finish a job in 6 days. How many more hours a day must 8 (answered by ankor@dixie-net.com)
It takes 6 days to clean a house working 4 hours per day. How many days will it take to... (answered by Fombitz)