SOLUTION: A contractor is paid the value of a contract less a penalty for each day that he is late in completing the contract. If the contractor is 4 days late, he receives £110,000 and if t
Algebra.Com
Question 1096573: A contractor is paid the value of a contract less a penalty for each day that he is late in completing the contract. If the contractor is 4 days late, he receives £110,000 and if the contractor is 10 days late, he receives £80,000. Calulate the value of the contract and the daily penalty.
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
c-4p=110000
c-10p=80000
RELATED QUESTIONS
A building contractor agrees to pay a fine for all the days he is late completing a job. (answered by richwmiller)
Gonzales Construction contracted Kentwood High and Memorial Stadium for a total cost of... (answered by josmiceli)
The probability that a contractor will win a bid for contract A is 0.45; the probability... (answered by stanbon)
A contractor has submitted bids for two state construction projects. The probability that (answered by Fombitz)
A contractor forfeits 30% on any overdue contract. If a contract worth $ 25 000 is... (answered by fractalier)
A contractor has submitted bids for two state construction projects. The probability of... (answered by ikleyn)
Tom is a medical equipment salesman and must choose between two salary contracts. In... (answered by checkley79)
A contractor has submitted bids for two state construction projects. The probability that (answered by Boreal)
A contractor has submitted bids for two state construction projects. The probability that (answered by rothauserc)