SOLUTION: Six workers can paint 4 houses in 8 days. ahow many additional workers are neededi if the job of painting 8 houses must be finish in 4 days?

Algebra.Com
Question 1028207: Six workers can paint 4 houses in 8 days. ahow many additional workers are neededi if the job of painting 8 houses must be finish in 4 days?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Six workers can paint 4 houses in 8 days.
how many additional workers are needed if the job of painting 8 houses must be finish in 4 days?
:
Find how many man-days required for each house
= 12 man-days per house
then
12 * 8 = 96 man-days to paint 8 houses
:
let w = no. additional workers required
4(w+6) = 96
4w + 24 = 96
4w = 96 - 24
4w = 72
w = 72/4
w = 18 additional men required

RELATED QUESTIONS

Six workers can paint 4 houses in 8 days. How many additional workers are needed if the... (answered by edjones)
Five workers paint four houses in six days. Working at the same rate as these workers,... (answered by promotion analysis,ankor@dixie-net.com)
If 15 workers can paint 18 houses in 24 days, how many days will 40 workers take to paint (answered by stanbon)
If 15 workers can paint a certain number of houses in 24 days, how many days will 40... (answered by fractalier)
three workers can paint a house in 14 days. assuming that the workers work at the same... (answered by josmiceli)
8 workers can paint a building in 24 days.How many days will 18 workers take to paint the (answered by Theo)
A group of 40 workers can finish digging a tunnel in 12 days. how many workers can... (answered by Edwin McCravy)
If 4 workers can paint a house in 8 hours, then 2 workers can paint the same house in... (answered by ptaylor)
if 3 workers can finish painting a house in 2 days, how many days will it take 6 workers (answered by josgarithmetic,josmiceli,ikleyn)