Question 942153: If it takes 3men 56hours to dig a hole 4mX6mX5m, and two of the men work twice
as fast as the third,find the number of hours that will take the two faster men to dig this hole together. ( answer is 70hours - show your solution )
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
Let = the rate of working of the slow man
= the rate of working of the two faster men
-----------------
Add their rates of working to get rate working together
It takes 70 hrs for the 2 faster men digging together
---------------
check:
OK
RELATED QUESTIONS
If it takes 3men 56hours to dig a hole 4mX6mX5m, and two of the men work twice
as fast... (answered by lwsshak3)
If it takes 3men 56hours to dig a hole 4mX6mX5m, and two of the men work twice
as fast... (answered by ankor@dixie-net.com)
Tom, Dick, and Harry begin working together to dig a trench. Tom works twice as fast as... (answered by ankor@dixie-net.com)
if 38 men working 6hr a day can do a piece of work in 12days,find in what time 57 men... (answered by ankor@dixie-net.com)
If it takes 8 men 9 hours to dig a hole in 20 minutes,how long would it take 10 men to... (answered by josgarithmetic)
If it takes 8 men 9 hours to dig a hole in 20 meters deep,how long would it take 10 men... (answered by ankor@dixie-net.com)
if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
Answer this school maths question - If it takes three men three hours to dig a hole, how... (answered by ankor@dixie-net.com)
2. If it takes 6 men working 6 hours each to dig a hole in the ground, then how long will (answered by venugopalramana)