Question 1136507: If 15 men , woking 9 hours a day, can reap a field in 16 days , in how many days will 18 men reap the field , working 8 hours a day ?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
If 15 men, working 9 hours a day, can reap a field in 16 days, in how many days will 18 men reap the field, working 8 hours a day?
:
Find the no. of man-hours required to do the field
15*9*16 = 2160 man hrs
:
let d = no. of day required with 18 men working 8 hrs a day
18*8*d = 2160
144d = 2160
d = 2160/144
d = 15 days
:
Check: 18 * 8 * 15 = 2160
RELATED QUESTIONS
if 8 men working 9 h a day can reap a field in 24 day in how many day will 12 men reap... (answered by josgarithmetic)
15 labourers working 9 hours daily can reap the field in 8 days. find how many workers... (answered by ankor@dixie-net.com)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
If 8 men could plough a field in 9 days, how many days would it take 18 men working at... (answered by neatmath)
20 men can reap a field in 20 day.when should 5 men leave the work,if the whole field is... (answered by ankor@dixie-net.com)
Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
Working 8 hours a day, 24 men do a piece of work in 15 days. Find how many days it would... (answered by ewatrrr)
If 12 men mow a field of 40 acres in 8 days working 10 hours a day how many days will it... (answered by ankor@dixie-net.com,stanbon)
If 10 men earn Rs 1,800 in 18 days, working 6 hours a day, how much will 15 men earn in... (answered by Boreal)