SOLUTION: 15 Java programmers, working in a constant pace, finish a web page in 3 days. If
after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the
Algebra.Com
Question 446845: 15 Java programmers, working in a constant pace, finish a web page in 3 days. If
after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the job?
Answer by mohammadrezai(14) (Show Source): You can put this solution on YOUR website!
Whole the work needs 45 man/day work.
And after 1 day, 15 man/day done and 30 man/day work remained.
There for 6 programmers must 5 day work that the work completed.
RELATED QUESTIONS
A project requires 2 web programmers, 3 mobile programmers, and 1 the database... (answered by ikleyn)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
A firm has an opening for 3 computer programmers and there are 20 applicants. In how... (answered by longjonsilver)
3.Among employees of a certain firm, 70% know C/C++, 60% know Java, and 50% know both... (answered by jrfrunner,ValerieDavis)
1.The Java computer language, developed by Sun Microsystems, has the advantage that its... (answered by Boreal)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
if 6 men can paint a fence in 2 days. how many men working at the same time uniform rate... (answered by colliefan)
Hi
it takes 15 days for 10 workers working 8 hours a day to finish an order. How many... (answered by joshuajz,josgarithmetic,ikleyn,greenestamps)