SOLUTION: A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it?
Algebra.Com
Question 874737: A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it?
Answer by rothauserc(4718) (Show Source): You can put this solution on YOUR website!
A + B = 72
B + C = 120
A + C = 90
therefore
B = 120 - C
C = 90 - A
B = 120 - 90 + A = 30 + A
A + 30 + A = 72
2A = 42
A = 21 days
RELATED QUESTIONS
A and B can do a piece of work in 12 days , B and C can do it in 15 days and C and A can... (answered by richwmiller)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a... (answered by ikleyn)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In... (answered by Edwin McCravy,AnlytcPhil,Edwin Parker)