Question 815711: p&q can do a piece of work in 10 days, q&R in 12 days while p&R can do it in 12 days .in how many days p alone can do the work
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
p&q can do a piece of work in 10 days, q&R in 12 days
while p&R can do it in 12 days, in how many days p alone can do the work
:
let the completed job = 1
:
"p&q can do a piece of work in 10 days,"
+ = 1
:
q&R in 12 days
+ = 1
:
while p&R can do it in 12 days
+ = 1
:
in how many days p alone can do the work
we know that
+ = +
if we subtract 12/r from both sides
=
therefore: q = p
Replace q with p in the 1st equation
+ = 1
= 1
p = 20 days for p to do it alone
RELATED QUESTIONS
p & q together can do a work in 32 days,p and r together in 48 days, r &q together in 24... (answered by richwmiller)
P can do a piece of work in 20 days and Q in 24 days. (answered by richwmiller)
P, Q, R together can build a house in 8 days. P & Q can build the house separately in 20... (answered by richwmiller)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
P can do a piece of work in 20 days (answered by richwmiller)
3. P can do a piece of work in 9 days. Q is 50% more efficient than P. The number of days (answered by MathLover1)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)