SOLUTION: An experienced roofer can roof a house in 26 hours. A beginning roofer needs 39 hours to complete the same job. How long does it take to do the job if the two work together?

Algebra.Com
Question 200412: An experienced roofer can roof a house in 26 hours. A beginning roofer needs 39 hours to complete the same job. How long does it take to do the job if the two work together?
Answer by solver91311(24713)   (Show Source): You can put this solution on YOUR website!


If A can do a job in x time periods, then A can do of the job in 1 time period. Likewise, if B can do the same job in y time periods, then B can do of the job in 1 time period.

So, working together, they can do



of the job in 1 time period.

Therefore, they can do the whole job in:



time periods.


John


RELATED QUESTIONS

An experienced roofer can roof a house in 26 hours. A beginning roofer needs 39 hours to... (answered by tinkerbell146,ankor@dixie-net.com,stanbon,richwmiller)
an experienced roofer can work twice as fast as helper. working together, they can... (answered by Boreal)
A roofer requires 15 hours to shingle a roof. And apprentics roofer can do tthe job in 21 (answered by stanbon,Theo)
Construction A roofer requires 12 hours to shingle a roof. After the roofer and an... (answered by scott8148)
A roofer and an assistant can repair a roof together in 8 hours. Working alone, the... (answered by lwsshak3)
A roofer and an assistant can repair a roof together in 7 hours. Working alone, the... (answered by mananth)
A roofer and an assistant can repair a roof tegether in 6 hours. The assistant can... (answered by josgarithmetic,MathTherapy)
A roofer and an apprentice are roofing a newly constructed house. In one day, the roofer... (answered by Boreal)
A roofer requires 12 hours to shingle a roof, working alone. After the roofer and his... (answered by josgarithmetic)