SOLUTION: 120 men can do a work in 90 days,how many more men required to complete the same work in 40 days?

Algebra ->  Algebra  -> Proportions  -> Lessons  -> Proportions -> SOLUTION: 120 men can do a work in 90 days,how many more men required to complete the same work in 40 days?      Log On

Ad: Algebra Solved!™: algebra software solves algebra homework problems with step-by-step help!
Ad: Algebrator™ solves your algebra problems and provides step-by-step explanations!

   


Question 15022: 120 men can do a work in 90 days,how many more men required to complete the same work in 40 days?
Answer by fractalier(2101) About Me  (Show Source):
You can put this solution on YOUR website!
This problem is done in terms of man-days...
If 120 men can do it in 90 days, it takes 120 x 90 = 10800 man-days to do the job.
Thus you need 10800 man-days / 40 days = 270 men