Question 878757: Hi everyone I need help in this bukit panjang govt high school 2013 prelim Emaths qns :
12 men planned to complete building a shed in 15 days. Only 1/3 of the shed was built at the end of 6 days due to poor weather conditions. Assuming that all men worked at the same rate, how many more men were needed for the rest of the job to be completed as scheduled ?
Thank you and appreciate your help rendered 😊

Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!
 
Hi


= 16 men (4 more men needed to finish the rest)
RELATED QUESTIONS

Hi I really need help asap in this trigo problem! And my trigo test is coming soon and... (answered by ewatrrr)
Hi everyone, This is my problem, I need to transform the following equation from... (answered by scott8148)
HI Everyone! I actually need help with my English homework and know there are alot of... (answered by Nate)
I cannot figure out how to solve this problem. Can anyone help? The senior classes ot... (answered by scott8148)
I need help in understanding the steps to complete this problem 4x+6y=24... (answered by J2R2R)
hi my name is miralin and i,m in high school and i need help with math i dont understand... (answered by ankor@dixie-net.com)
4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which... (answered by josmiceli,MathTherapy)
Im a sophomore in High school and i need help in Algebra like... (answered by Edwin McCravy)
tutors help me with this plz... i tried to solve it but i didn't get the right... (answered by ankor@dixie-net.com)