SOLUTION: in a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine candy. How long would it take if there were 30 workers?

Algebra.Com
Question 74977: in a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine candy. How long would it take if there were 30 workers?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
n a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine candy. How long would it take if there were 30 workers?
:
Represent the completed job in "man-days"
In this problem:
20 * 6 = 120 man-days
:
How many days to complete the same job with 30 men?
30*d = 120
d = 120/30
d = 4 days to do the same job with 30 guys.

RELATED QUESTIONS

In a chocolate factory, 3 employees can manufacture 20 packs of chocolate in one hour.... (answered by ikleyn)
A candy factory has a large vat into which workers pour chocolate and cream. Each... (answered by stanbon)
if it takes 6 days for 6 workers to build a garage, how long would it take 9... (answered by Edwin McCravy,ikleyn,greenestamps)
how long will it take 8 workers to complete a job that took 5 workers to complete in 10... (answered by richwmiller)
Suppose that 6 workers can complete a certain task in 10 days. If there are 20 (answered by josgarithmetic)
it took 4 workers 9 days to complete a renovation work.how many workers would it take to... (answered by josgarithmetic)
1.Eight workers can paint an entire house in ten hours. How long would it take five... (answered by stanbon)
at the valve factory w workers made v valves in 5 days how many days would it take n more (answered by ankor@dixie-net.com)
A company that supplies bulk candy to bakeries has one batch of chocolate chips that are (answered by stanbon,Finavon)