SOLUTION: 18 men can dig a ditch in 10 days. After they have worked for 4 days how many more men shall be employed to complete the work in 4 days from then?
Algebra.Com
Question 472609: 18 men can dig a ditch in 10 days. After they have worked for 4 days how many more men shall be employed to complete the work in 4 days from then?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
18 men can dig a ditch in 10 days.
After they have worked for 4 days how many more men shall be employed to complete the work in 4 days from then?
:
Determine the no. of man-days required to do the job
18 * 10 = 180 man-days
:
Let m = no. of additional men required to complete the job in 4 more days
The original 18 men will work a total of 8 days
:
(18*8) + 4m = 180
144 + 4m = 180
4m = 180 - 144
4m = 36
m =
m = 9 men required
:
:
Check this by finding the total man-days
18*8 + 9*4 = 180
RELATED QUESTIONS
if 6 men can dig a ditch in 4 days,how many mens can dig the same ditch in 3 days (answered by Boreal,greenestamps)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
16 men can finish a work in 12 days. After they worked for 4 days, some more men joined... (answered by ikleyn,josgarithmetic)
17 men can dig a ditch 26m long in 18 days , working 8 hours a day . How many more men... (answered by josmiceli)
7 men can dig a drain in 10 days. how many men would dig the same drain in 14 days
(answered by josgarithmetic,ikleyn,greenestamps)
A contractor engages 16 men to build a wall 80 metres long and estimated that they will... (answered by ewatrrr)
20 men finished 1/4 of the house in 7 days.but they have to finish it in 5 more days. how (answered by stanbon)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)