SOLUTION: 15 labourers working 9 hours daily can reap the field in 8 days. find how many workers are required to reap such 5 fields working 12 hours daily in 15 days?

Algebra.Com
Question 422801: 15 labourers working 9 hours daily can reap the field in 8 days. find how many workers are required to reap such 5 fields working 12 hours daily in 15 days?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
15 labourers working 9 hours daily can reap the field in 8 days. n 15 days?
:
Find how many man-hrs required to complete one field
15 * 9 * 8 = 1080 man-hrs
:
"find how many workers are required to reap such 5 fields working 12 hours daily in 15 days?"
:
Let w = no. of workers to do this
:
12*15*w = 5(1080)
180w = 5400
w =
w = 30 workers

RELATED QUESTIONS

If 15 men , woking 9 hours a day, can reap a field in 16 days , in how many days will 18... (answered by ankor@dixie-net.com)
if 8 men working 9 h a day can reap a field in 24 day in how many day will 12 men reap... (answered by josgarithmetic)
If 5 men and 3 boys can reap 23 acres in 4 days and 3 men and 2 boys can reap 7 acres in... (answered by ikleyn)
I have exam tomorrow. Please help me tutors. 1)AOB is a straight line. Find z if x=35... (answered by fcabanski)
20 men can reap a field in 20 day.when should 5 men leave the work,if the whole field is... (answered by ankor@dixie-net.com)
if three people can harvest the field in 8 days, how many people are needed to harvest... (answered by josmiceli)
8 labourers cut a field in 6 days. (a) how many men will cut the field in 3 days? (b)... (answered by josgarithmetic,ikleyn)
Hi it takes 15 days for 10 workers working 8 hours a day to finish an order. How many... (answered by joshuajz,josgarithmetic,ikleyn,greenestamps)
Ten Painter Working 8 Hours Daily take 15 Days To paint 3 Houses Of 4 Rooms Each. How... (answered by ankor@dixie-net.com)