SOLUTION: John can do a piece of work in 8 days and peter can do the same piece of work in 6 days.They work together on it for two days and then peter stops working altogether.How long will
Algebra.Com
Question 353154: John can do a piece of work in 8 days and peter can do the same piece of work in 6 days.They work together on it for two days and then peter stops working altogether.How long will it take for john to complete the remaining part of the work by himself?
Answer by Fombitz(32388) (Show Source): You can put this solution on YOUR website!
Rate*Time=Output
.
.
.
Let be the number of worker-days to do the work.
For John,
For Peter,
When they work together for 2 days,
The work that remains is,
Find the time it takes John to finish it,
days
RELATED QUESTIONS
Peter can do a piece of work in 8 days, sam in 10 days and john in 16 days. Sam and john... (answered by josmiceli)
peter can do a piece of work
in 8 days sam in 10 days and john in 16 days
sam adams... (answered by josgarithmetic)
If Mario can do a piece of work in 3 days and Joey in 2 days, in how many days can they... (answered by Alan3354)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
John can do a piece of work in 15 days. John and David can do the same amount work in 6... (answered by Edwin McCravy)
Artesia can do a piece of work in 10 days. After she has worked in two days, Fate came to (answered by josgarithmetic)
John can complete a piece of work in 3 days. Jojce can do it in 9 days and James can do... (answered by ewatrrr)