Answer by Alan3354(69443) (Show Source): You can put this solution on YOUR website!
24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per days do the same work.
------------------------
The job takes 24 men x 8 hrs/day x 15 days = 2880 man-hours
------------
2880 man-hours/(20 men x 9 hours/day) = 16 days
-----------------------
Another method:
15 days * 24/20 * 8/9 = 16 days
RELATED QUESTIONS
15 men working 6 hours a day can do a piece of work in 20 days. how many men working 8... (answered by sadike007)
Working 8 hours a day, 24 men do a piece of work in 15 days. Find how many days it would... (answered by ewatrrr)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
If 12 men working 8hrs a day can do a piece of work in 15 days, how many hrs a day must... (answered by stanbon)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
It will take 24 men working 9 hours a day each to build a house in 45 days. Given that... (answered by lwsshak3)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
5 men, 20 women and 40 boys can do a piece of work in 120 days working 6 hrs a day. In... (answered by jorel555)