Question 238447: Thirty men take 20 days to complete a job working 9 hours a day. How
many hours a day should 40 men work to complete the job?

Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Thirty men take 20 days to complete a job working 9 hours a day.
How many hours a day should 40 men work to complete the job?
:
The easiest way to do this is use "man-hours"
:
30 * 20 * 9 = 5400 man-hours required to complete the job
:
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x =
x = 6.75 hrs a day for 20 days to do the same job

RELATED QUESTIONS

If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)
25 men take 20 days working 8hours a day to complete a job.how many days will 15 men take (answered by ptaylor)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)
A block industry estimates that 10 men must work for 8 hours each day to complete a job... (answered by ankor@dixie-net.com)
A cement factory estimates that 10 men must work for 8 hours each day to complete a job... (answered by josgarithmetic)
Ten men working six hours a day takes 12 days to complete the job.How long will it take... (answered by josgarithmetic)
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 (answered by vksarvepalli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)