SOLUTION: It takes 3 people to clean a pool in 4 hours. How many people do we need to clean 6 pools in 8 hours?
It seems to be a triple proportion but how exactly would I set it up?
Question 1165522: It takes 3 people to clean a pool in 4 hours. How many people do we need to clean 6 pools in 8 hours?
It seems to be a triple proportion but how exactly would I set it up?
Rate for 1 worker, r
number of workers, n
rate for n workers, nr
---------------------------------------------------------------------------
It takes 3 people to clean a pool in 4 hours. How many people do we need to clean 6 pools in 8 hours?
-------------------------------------------------------------------------