SOLUTION: If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take for 10 men to dig a hole 7 metres deep?

Algebra.Com
Question 1144061: If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take for 10 men to dig a hole 7 metres deep?

Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39614)   (Show Source): You can put this solution on YOUR website!
r, the one-man digging rate













-

(number seems strange. Look for any mistakes in steps.)

Answer by ikleyn(52756)   (Show Source): You can put this solution on YOUR website!
.

From the first statement, the rate of work is   =  =  meter per one man per day.


Let the number of days is x.  Then the equation to find the unknown x is


     = 7,


which gives


    x =  =  =  days =  days = 5.6 days.    ANSWER


/\/\/\/\/\/\/\/

Be aware (!) :   writing by @josgarithmetic is   WRONG  and  INCORRECT   from the first line to the end.

For your safety,  ignore his post.



RELATED QUESTIONS

If it takes two men two hours to dig a hole 3 metres long, 3 metres wide and 3 metres... (answered by josgarithmetic)
if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
if it takes 4 men 12 days to dig a hole, how long would it take 6... (answered by ptaylor)
10 men take 7 days to dig a hole. how many days will it take 4 men to dig the same hole... (answered by stanbon)
If it takes 8 men 9 hours to dig a hole in 20 meters deep,how long would it take 10 men... (answered by ankor@dixie-net.com)
if it takes 7 men 3 hours to dig a hole, how long will it take 2 men ? (answered by josmiceli)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If it takes 2 men 2 hours to dig a hole 3 foot long, 3 foot wide, 3 foot deep. How long,... (answered by solver91311)
If it takes two men three hours to dig a hole 4 meter long, four meters wide, and four... (answered by god2012)