SOLUTION: If 8 people do a piece of work in 12 days, how many people will be needed to do the same work in 16 days?
Algebra
->
Proportions
-> SOLUTION: If 8 people do a piece of work in 12 days, how many people will be needed to do the same work in 16 days?
Log On
Algebra: Proportions
Section
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Proportions
Question 109042
:
If 8 people do a piece of work in 12 days, how many people will be needed to do the same work in 16 days?
Answer by
scott8148(6628)
(
Show Source
):
You can
put this solution on YOUR website!
the work takes 96 (8*12) people-days (like man-hours)
if you have 16 days, you need 96/16 or 6 people
let x=people ... 8*12=x*16