Question 109042: If 8 people do a piece of work in 12 days, how many people will be needed to do the same work in 16 days?
Answer by scott8148(6628)   (Show Source): You can put this solution on YOUR website!
the work takes 96 (8*12) people-days (like man-hours)

if you have 16 days, you need 96/16 or 6 people

let x=people ... 8*12=x*16

RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
7 men can do a piece of work in 12 days. How many men will be required to do double the... (answered by mbgupta@hotmail.com,ramkikk66)
If 12 men do a piece of work in 80 days. In how many days will 16 men do... (answered by stanbon)
If 6 men can do a piece of work in 14 days, how many men are needed to do the same work... (answered by tutorcecilia,ptaylor)
if four men do a piece of work in 8 days how many days will it take 16 men working at the (answered by ewatrrr)
12 workers can do a piece of work in 16 days if 12 more workers are added in how many... (answered by Cromlix)
if 800 people can do a piece of work in 80 days.after 5 days 50 people left.How much more (answered by josgarithmetic)
10 people can do half of the work in 7 days ? how many days will take to do the same work (answered by mananth)
If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21... (answered by ankor@dixie-net.com)