Question 1078849: A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they work for 8 hours per day. After 20 working days, he finds that only 1200 m of the road is completed. How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
A contractor agrees to lay a road 3000 m long in 30 days.
50 men are employed and they work for 8 hours per day.
After 20 working days, he finds that only 1200 m of the road is completed.
How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?
:
Find how many man-hrs needed to complete 1200 meters
50 * 8 * 20 = 8000 man-hrs
Find how many man-hrs per meter
8000/1200 = 6.67 man-hr per meter
then find how many for the remaining 1800 meters
6.67 * 1800 = 12000 man-hr required to complete the job
:
let m = the additional men required working 10 hrs a day for the 10 days left on the contract
(50+m) * 10 * 10 = 12000
100(50+m) = 12000
50 + m = 12000/100
50 + m = 120
m = 120 - 50
m = 70 additional men required
RELATED QUESTIONS
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A block industry estimates that 10 men must work for 8 hours each day to complete a job... (answered by ankor@dixie-net.com)
A cement factory estimates that 10 men must work for 8 hours each day to complete a job... (answered by josgarithmetic)
A contract is to be completed in 56 days and 104 men were set to work, each working 8... (answered by josgarithmetic)
A road contractor wanted to build a 200 meter long road in 30 days and employed 20... (answered by ankor@dixie-net.com,MathTherapy)
A contractor engages 16 men to build a wall 80 metres long and estimated that they will... (answered by ewatrrr)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)