Question 1061550: A contractor engaged 30 persons to construct the road in 30 days but only one fourth of the work was completed after 10 days. How many more persons are required to complete the work in time?
Answer by jorel555(1290) (Show Source): You can put this solution on YOUR website!
If only 1/4th of the work is done in 10 days, then it takes 40 days to finish the work. 30 people doing 1/40th of the work per day is 1/30 x 1/40, or 1 person doing 1/1200th of the work per day. Let n be the number of people needed. Then:
n/1200 x 20=3/4
80n=3600
n=45
You need 45 people to do the job, or 15 more people than the 30 you already have. ☺☺☺☺
RELATED QUESTIONS
A contractor was engaged to finish 6km of railway line in 210 days; but after employing... (answered by josgarithmetic)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A road contractor wanted to build a 200 meter long road in 30 days and employed 20... (answered by ankor@dixie-net.com,MathTherapy)
a contractor got a contract to build a building in 30 days and employed 20 men to do the... (answered by ankor@dixie-net.com)
a contractor engages 24 workers to build a road in 30 days. after 24 days he finds... (answered by TimothyLamb)
A contractor undertook to build a road in 200 days he employed 140 men after 60 days he... (answered by josgarithmetic,josmiceli,ikleyn,MathTherapy)