Question 1036554: A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they work for 8 hours say. After 20 working days, he finds that only 1200 m of the road is completed. How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
A contractor agrees to lay a road 3000 m long in 30 days.
50 men are employed and they work for 8 hours say. After 20 working days, he finds that only 1200 m of the road is completed.
:
Find the number of man-hrs required to complete 1200 meters
50*8*20 = 8000 man-hrs
Find the no. of meters per man-hr
= .15 meters per per man-hr
:
How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?
Find how many man-hr required to do the remaining 1800 meters
= 12000 man-hrs
let m = no. of additional men required to accomplish this in 10 days working 10 hrs a day
10*10*(m+50) = 12000
100m + 5000 = 12000
100m = 12000 - 5000
100m = 7000
m = 7000/100
m = 70 more men
RELATED QUESTIONS
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A road contractor wanted to build a 200 meter long road in 30 days and employed 20... (answered by ankor@dixie-net.com,MathTherapy)
a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
30 men can do a work in 36 days. After 30 days more men are employed and work is done 2... (answered by josmiceli)
a contractor got a contract to build a building in 30 days and employed 20 men to do the... (answered by ankor@dixie-net.com)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)
A block industry estimates that 10 men must work for 8 hours each day to complete a job... (answered by ankor@dixie-net.com)