SOLUTION: If 15 men complete a work in 20 days then 25 men will complete that work in how much days..?

Algebra.Com
Question 1022752: If 15 men complete a work in 20 days then 25 men will
complete that work in how much days..?

Found 3 solutions by FrankM, Edwin McCravy, AnlytcPhil:
Answer by FrankM(1040)   (Show Source): You can put this solution on YOUR website!
15 men * 20 days to do one job means it requires 300 man-days to do the job.
300 man-days/25 men = 12 days

Answer by Edwin McCravy(20055)   (Show Source): You can put this solution on YOUR website!
Here are two more ways to do it:

The least common multiple of 15 men and 25 men is 75 men

If 15 men complete a work in 20 days
Then 5 times as many men, or 75 men, can do it in 1/5th the time, or 4 days

then 25 men will complete that work in how much days..?
25 men is 1/3rd of 75 men so it will take them 3 times as long, or 12 days.

---------------------
OR
---------------------
The greatest common factor of 15 men and 25 men is 5 men

If 15 men complete a work in 20 days
Then 1/3 as many men, or 5 men, will take 3 times as long, or 60 days

then 25 men will complete that work in how much days..
25 men is 5 times as many men as 5 men, so it will take them 1/5 as long, 
or 12 days.

Edwin

Answer by AnlytcPhil(1806)   (Show Source): You can put this solution on YOUR website!
Here is the way your teacher most probably wants you to
solve it:

The number of workers and the number of days required
are inversely proportional (one increases if the other
decreases), so we set up the proportions in reverse
order:



Let the number of days the SECOND time be N



Cross-multiply:



Divide both sides by 25





So it will take 12 days.

Edwin

RELATED QUESTIONS

If 15 men complete a work in 20 days;then 25 men will complete that work in how much... (answered by josgarithmetic)
If 15 men complete a work in 20 days, then how many men will be required to do the same... (answered by josgarithmetic)
if 5 men complete work in 100 days than how many men complete the same work in 20 days ? (answered by richwmiller)
if 15 men can do a work in 210 days . they started working but at the end 10 days 15... (answered by josgarithmetic)
if 8 men or 12 women can complete a work in 25 days than 6 men and 11 women will complete (answered by richwmiller)
10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be (answered by ankor@dixie-net.com)
If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
If 20 men complete one third of a piece of work in 20 days, how many more men should be... (answered by jorel1380)