Question 1022537: If 15 men complete a work in 20 days;then 25 men will complete that work in how much days.
Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
N*R*T=W relates N workers each with rate of R for time T producing W amount of work or jobs.

Let r be the one man rate and let t be number of unknown days.
The description leads to .
The question asks for t; but you can also find r.

RELATED QUESTIONS

If 15 men complete a work in 20 days then 25 men will complete that work in how much... (answered by FrankM,Edwin McCravy,AnlytcPhil)
If 15 men complete a work in 20 days, then how many men will be required to do the same... (answered by josgarithmetic)
if 5 men complete work in 100 days than how many men complete the same work in 20 days ? (answered by richwmiller)
if 15 men can do a work in 210 days . they started working but at the end 10 days 15... (answered by josgarithmetic)
if 8 men or 12 women can complete a work in 25 days than 6 men and 11 women will complete (answered by richwmiller)
10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be (answered by ankor@dixie-net.com)
If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
If 20 men complete one third of a piece of work in 20 days, how many more men should be... (answered by jorel1380)