Question 862911: 24 men complete a job in 40 days. The number of men required to complete the job in 32 days is
Answer by JulietG(1812) About Me  (Show Source):
You can put this solution on YOUR website!
The job takes 40 days * 24 men, or 960 man-days (usually it's easier to work in man-hours, but this question is days)
960 man-days / 32 days = 30 men