SOLUTION: 24 men complete a job in 40 days. The number of men required to complete the job in 32 days is

Algebra.Com
Question 862911: 24 men complete a job in 40 days. The number of men required to complete the job in 32 days is
Answer by JulietG(1812)   (Show Source): You can put this solution on YOUR website!
The job takes 40 days * 24 men, or 960 man-days (usually it's easier to work in man-hours, but this question is days)
960 man-days / 32 days = 30 men

RELATED QUESTIONS

5 men are hired to complete a certain job. if an additional men is hired, the job can be... (answered by ikleyn)
Y men can do a job in 20 days. They work for 8 days and rest for 4 days. For them to... (answered by ankor@dixie-net.com)
If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
Fifteen carpenters can complete building a house in 45 days . How many extra men will be... (answered by ankor@dixie-net.com)
If 7 men complete a job in 12 days. How many more men are required to complete that same... (answered by Cromlix)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
eight men can complete a job in 25 days. how many men will be needed to complete the job... (answered by psbhowmick)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)