SOLUTION: 36 man can do a work in 20 days,in how many days 24 man do the same work ,given that time spent per day is decreased by 1/3 of the previous time?
Algebra.Com
Question 773568: 36 man can do a work in 20 days,in how many days 24 man do the same work ,given that time spent per day is decreased by 1/3 of the previous time?
Answer by josgarithmetic(39613) (Show Source): You can put this solution on YOUR website!
There are given normal work day and (1/3) workday.
Normal Day:
36 men, 1 job, 20 days.
For 1 man, 1 job done in 20*36 days, or jobs per day.
Shorter workday:
The one-man rate will now be jobs per short-workday.
24 men working in these short-days makes their group rate jobs per short-day.
ANSWER: The group of 24 men doing the job using short (1/3) days needs 90 days to do this job.
RELATED QUESTIONS
5 man do a work in 30 days .how many man needed to do that work in 1... (answered by Cromlix)
If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then the same piece of... (answered by ptaylor)
a man can complete a work in 5days another man can do the same work in 8days In how many... (answered by josmiceli)
A job can be done by 15 men in 30 days. In how many days can 12 men complete the job,... (answered by Edwin McCravy)
Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
If 6 men can do a work in 20 days and one man can do t he work f two boys then in how... (answered by ankor@dixie-net.com)
3 man can can do as much work as 5 women and 1 women can do as much work as 2 children.... (answered by josgarithmetic)
if a man and a boy can do a work in 8 days,this work can do 2 man and 4 boy in 3 days... (answered by josmiceli)