Question 515208: If Sam can do the job in 6 days.. carla can do it in 4 days... John can do it in 2 days. How many days do they need .. if they do it together..
Found 2 solutions by scott8148, oberobic:
Answer by scott8148(6628) (Show Source): You can put this solution on YOUR website!
they each do a fraction of the task based on their individual rates; the fractions sum to one, the whole task
(x/6) + (x/4) + (x/2) = 1
2x + 3x + 6x = 12
Answer by oberobic(2304) (Show Source): You can put this solution on YOUR website!
The problems hinge on the fraction of work each can do per day, times the number of days.
.
(1/6 + 1/4 + 1/2)x = 1 whole job
.
(2/12 + 3/12 + 6/12)x = 1
.
11/12*x =1
.
11x = 12
.
x = 12/11
.
So working together they can do the job in 12/11 of a day.
.
Done.
RELATED QUESTIONS
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ntnk)
Sam does the job in 4 days that Lisa can do in 6 days that Tom can do in 2 days. How long (answered by nerdybill)
sam can do job in 4 days, Lisa - 6 days, Tom - 2 days. How long would the job take to... (answered by ewatrrr)
If Sam can do a job in 4 days, Lisa can do the same job in 6 days, and Tom can do the job (answered by stanbon)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by chitra)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ankor@dixie-net.com)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ptaylor)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by Mathtut)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by stanbon)