SOLUTION: It takes 5 men to build a shed in 120 days, how long does it take 3 men?

Algebra.Com
Question 478785: It takes 5 men to build a shed in 120 days, how long does it take 3 men?
Answer by Tatiana_Stebko(1539)   (Show Source): You can put this solution on YOUR website!
In 1 day 5 men do part of job, so in 1 day 1 man does part of job, then 3 men will do in 1 day part of job, then all job they will do in days
RELATED QUESTIONS

if it takes 4 men to build a shed in 9 hours, how long will it take 6... (answered by Cromlix)
4 men can build a shed in 12 days. How many men will it take to build the same shed in 3 (answered by josmiceli)
3 men build a house in 10 days . how long would it take 5... (answered by ankor@dixie-net.com)
If 3 men build a wall in 4 days how long will it take 5... (answered by josmiceli)
If it takes 3 men 4 days to build a wall how long will it take 2... (answered by stanbon)
it takes 8 men to build a wall in 30 days. How long would it take 10 men to build the... (answered by JulietG)
If it takes 6 men 12 days to build a wall, how long will it take 12... (answered by fcabanski)
It takes five men one hundred and twenty days to bild a shed, how many days does t take... (answered by Alan3354)
If it takes 5 men 6 days to build a house, how many days will it take if only 3 men are... (answered by ewatrrr)