.
A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men,
but 6 of them being absent from the very first day, the rest could finish the work in 15 days.
The number of men originally employed were:
~~~~~~~~~~~~~~~~~~~~~
x originally employed men;
So, the entire job was 9x men-days, as planned originally.
But it was done by (x-6) men in 15 days; hence
15*(x-6) = 9x.
From it,
15x - 90 = 9x,
15x - 9x = 90
6x = 90
x = 90/6 = 15.
ANSWER. 15 men were employed initially; but only 15-6 = 9 of them really worked.
Solved.