SOLUTION: Adil can do a job alone in 9 days while Babar can do it alone in 15 days Adil works alone on the job for x days after which Babar takes over and finishes the remainder of the job i

Algebra.Com
Question 1127014: Adil can do a job alone in 9 days while Babar can do it alone in 15 days Adil works alone on the job for x days after which Babar takes over and finishes the remainder of the job in 10 days find the value of x?
Found 3 solutions by josmiceli, greenestamps, ikleyn:
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
Adil's rate of working:
[ 1 job ] / [ 9 days ]
Babar's rate of working :
[ 1 job ] / [ 15 days ]
-----------------------------
Let = fraction of job that Adil completes
in days

multiply both sides by


Adil completes of the job, so
of the job is left
----------------------
Barbar does of the job in 10 days, so

Multiply both sides by



-------------------
Get a 2nd opinion if you can


Answer by greenestamps(13198)   (Show Source): You can put this solution on YOUR website!


I got lost trying to figure out the solution by the other tutor....

The problem is solved MUCH more easily if you start by figuring out the fraction of the job Babar does.

He takes 15 days to do the job alone; in the 10 days he worked, the fraction of the job he did was 10/15 = 2/3.

That means Adil did 1/3 of the job.

Since Adil would take 9 days to do the whole job alone, the number of days he worked to do 1/3 of the job was 9/3 = 3 days.

ANSWER: Adil worked on the job for 3 days.

Answer by ikleyn(52778)   (Show Source): You can put this solution on YOUR website!
.
Working for x days, Adil made    parts of the entire job.


Working 10 days,  Babar made    parts of the entire job.


It gives you an equation to find x:


     +  = 1.


From the equation,


     = 1 -  = 1 -  = ,


hence


    x =  = 3 days       Answer


RELATED QUESTIONS

Alan can do a piece of work in 15 days; Bill can do it in 20 days. If Alan works alone on (answered by josmiceli)
A can complete a job in 9 days, B can do the same job in 10 days and C can do it in 15... (answered by richwmiller)
Jim and Tom can do a job together in 12 days. After Tom has worked alone for 26 days, Jim (answered by richwmiller)
Mike and John can do a job together in 12 days. After John has worked alone 26 days,... (answered by scott8148)
manny and manuel can finish a certain job if manny works for 15 days and manuel works for (answered by greenestamps)
Manny and Manuel can finish a certain job if manny works for 15 days and Manuel works... (answered by greenestamps,ikleyn)
A man can do a job in 9 days and his son can do the same job in 16 days. They start... (answered by ptaylor)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by richwmiller)
Brenda can do a job in 10 days; Adam does the same job in 15 days. After Adam works alone (answered by scott8148)