Question 1036417: David can do a job in 15 days while ken can do the same job in 10 days.If both started the work together and ken quit after 2 days while david finished the job how long will the entire job take?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
David's rate of working:
[ 1 job ] / [ 15 days ]
Ken's rate of working:
[ 1 job ] / [ 10 days ]
---------------------
Add their rates of working to get their
rate working together
------------------
Their rate working together is:
[ 1 job ] / [ 6 days ]
------------------
In 2 days, the fraction of the job completed is
That means there is of the job left
after 2 days
-------------------------------------
Ken leaves after 2 days.
Let = time in days for David to finish the job
Multiply both sides by
David takes 10 days to finish the job
The entire job takes 12 days to finish
RELATED QUESTIONS
A can complete a job in 9 days, B can do the same job in 10 days and C can do it in 15... (answered by richwmiller)
Jose can do a certain job in 10 days, and Roy can do the same job in 12 days. If two men... (answered by ikleyn,Alan3354,greenestamps)
mr a can do a job for 3 days while mr b can do the same job for 6 days. if the two of... (answered by stanbon)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
Tom takes 3 days to do a piece of work while jerry takes only one day for the same.... (answered by ikleyn)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
joe can do a job in 3 days, while jill can do the same job in 6 days. How long will they... (answered by ikleyn)
tom takes 3days to do a piece of work while jerry takes only one day for the same.... (answered by josgarithmetic)
tom takes 3days to do a piece of work while
jerry takes only one day for the same.... (answered by josgarithmetic,ikleyn)